Data center
The data center: hall, racks, UPS, batteries, generators, cooling The data hall is the load. It holds about 320 racks and draws about 8 megawatts. Batteries follow the load, UPS units ride through dips, standby generators cover outages, and rooftop coolers reject the heat.
Open this system in 3D
Data hall The data hall holds the servers that use the reactor output. One microreactor carries roughly 8 MW of IT load plus cooling and losses.
Footprint ≈ 48 × 22 m IT load ≈ 8 MW Racks 320 at ≈ 25 kW each Uptime target Tier III, concurrently maintainable
Open in 3D →
Server racks Servers sit in rows of racks with hot-aisle containment. Cold air enters the front of each rack and hot air leaves into a sealed aisle.
Rows 8 rows × 40 racks Rack power ≈ 25 kW, liquid-ready Containment Hot aisle, doors at each end Distribution Overhead busway, A and B feeds
Open in 3D →
UPS & electrical room The electrical room receives the feed from the substation and conditions it. UPS units ride through short dips while the generators start.
UPS 2 × 5 MW, N+1 Ride-through ≈ 5 minutes at full load Switchgear 13.8 kV to 480 V Distribution PDUs feed the overhead busway
Open in 3D →
Battery storage Battery containers smooth the load the reactor sees. The reactor runs flat out, and the batteries absorb or supply the difference.
Capacity ≈ 10 MWh in 3 containers Power ≈ 5 MW Chemistry Lithium iron phosphate Role Load following and black start
Open in 3D →
Backup generators Standby generators cover the hall if the reactor or the line is out. With the reactor as prime power, they run only for tests.
Units 2 × 3 MW Fuel Diesel, 24 hours on site Start time < 10 s to full load Duty Standby, monthly test
Open in 3D →
Cooling plant Rooftop coolers reject the heat the servers make. Fans pull air across coils, and the chilled loop returns to the hall.
Heat rejected ≈ 9 MW Units 6 rooftop dry coolers Loop Warm water, 30 °C supply Water use None, dry cooling
Open in 3D →